Høglund Retrofit / Upgrade / Repower
Nordlys Retrofit
Høglund develops and delivers advanced maritime solutions
Description
Nordlys Retrofit
In September 2011 during a dry-dock period for three weeks, we replaced the old NordControl System onboard.
Vessel Information Built: 1993 Owner: Hurtigruten AS
“15th of September 2011, an engine room fire broke out on Hurtigruten’s MS NORDLYS off the coast of Norway. The ship was carrying 262 people and many were taken off in lifeboats before the ship arrived in Ålesund, some 230 miles north-west of Oslo. Two crew members have died and at least 16 people were reportedly injured as the blaze forced rescuers to evacuate more than 200 passengers from the NORDLYS”
After the fire, Høglund got the contract for the entire rebuilt of the Automation System onboard. We replaced the old damaged NordControl System onboard with the Høglund system.
The existing MaK-cabinets where damaged, so we also got the contract for a new Main Engine Control systems. We replaced the MaK-cabinets, which contained the Engine Safety System, RPM-Switch and the Pleiger Controllers.
Høglund has delivered following solutions:
- Integrated Automation System (IAS) & Control-system
- Power Management System (PMS)
- Clutch Control System
- HVAC System, with control off all ventilation fans and heating/cooling
- Safety System for the MaK main engines & Gear
- Safety Systems for the Bergen Aux Engines
- Energy Management System
- AC Compressor & Cargo Compressor, Control System
- GMR Playback Recorder, with 5 months recording of every signal every second
- Remote access, for remote service and support
In addition, we had to do some modifications in the main switchboard, where we installed Deif, GPU’s and FAS units for remote synchronization of generator and tie-breakers.
Old I/O Cabinet with controllers and I/O modules
Old alarm, computers and control panels in ECR desk
Old modules are replaced with new S800 hardware
New Høglund Control Cabinet with redundant controllers
New Høglund operation stations with wide screen monitors.
The fire on Hurtigruten’s MS NORDLYS
An engine room fire broke out on Hurtigruten’s MS NORDLYS
Damages after the fire
This was a "turn-key" contract. Høglund project and commissioning engineers arranged:
- Approbation with Factory Acceptance Test together with DNV-GL
- FAT
- Cable-pulling
- Installation, Reconnection and IO-Check
- Harbour Acceptance Test with DNV-GL
- Sea Acceptance Test with DNV-GL
After the sea-trial we handed over the new system with all approved certificates needed.
More from Høglund
- Hoglund Automation & Control
- Hoglund Cargo Control
- Hoglund cSafe Firewall
- Hoglund Engine Control and Safety System
- Hoglund Fuel Gas Control
- Hoglund HVAC Control
- Hoglund Integrated Automation System
- Hoglund Power Systems
- Hoglund Safety & Shutdown
- Hoglund Seismic Compressor Control
- Hoglund Ship Performance Monitor (SPM)
- Hoglund 5-year service
Featured services
All services →Retrofit / Upgrade / Repower
Make fuel flexibility a competitive advantage for power plants
Our gas conversion solutions can help you to maximize competitiveness and build a greener profile by capitalizing on optimal fuel prices and lowering emissions.
Maintenance / Service Agreement
Service excellence beyond turbochargers
Harness Accelleron’s global coverage and engineroom expertise to ensure other mission-critical engine components are running at optimal condition.
Similar services